Modernization photos will be updated here each week.  Come back to check on progress and enjoy seeing our school transformed throughout the summer months.  Click on the photo gallery to see pictures of the progress.
 
July 12, 2011-  New photos have been added!  The demolition phase is progressing well and on schedule.
 
July 19, 2011-  New photos have been added!  Look for the photos of framing and drywall additions.  The construction phase is well under way in the kindergarten and first grade wing. 

Aug. 15, 2011- New photos have been added! Cabinetry and carpet are now being installed in some classrooms and we have new asphalt for additional playground space in the back of the school. Modernization work is right on schedule for opening day.

Aug. 23, 2011- New photos have been added! New sod has been laid down and looks wonderful. Classrooms in the kinder wing are just being finished.
Oct. 1, 2011- All classrooms have been completed as well as the office and library areas. 
 
Feb. 14, 2012- The last of our temporary fencing has come down and all of our fields are available for our students and teachers to use.